Morson Projects were appointed by Sellafield Ltd to carry out the design, analysis, manufacture and CE marking for a new B13 Lifting Beam & Stand.
OUR SOLUTION
A bespoke adjustable lifting beam and park stand was required to support waste flasks during transportation operations on site. To enable the accurate design and implementation, our team delivered:
- WLL 15,000Kg (15 Tonnes)
- The design utilised adjustable trunnions, detailed markings and a leadscrew driven by a hand wheel which ensures correct alignment. These were all used to secure and balance different waste flask configurations.
- A full stress investigation completed to ensure suitability and conformance to regulations, including stress reports and a complete technical file.
Our services
Delivering the project requirements to an agreed Statement of Work (SOW), the Morson Projects team carried out services to include:
- Tooling Design & Manufacture
- Structural Design & Analysis